9-19-15 city of fdl weekly construction update

todaySeptember 19, 2015

West Division Street from Brooke Street east to the Fond du Lac River
Schedule:  April 20, 2015 to early October 2015
Description:  The project includes reconstruction of the sanitary sewer, water main, storm sewer, street, and lighting.
September 21 to September 25: The concrete subcontractor continues flatwork on sidewalks and aprons.
Traffic Impacts:  West Division Street is closed to through traffic. Residents, business owners, and customers may access properties past “ROAD CLOSED – LOCAL TRAFFIC ONLY” signs. Parking is not permitted on the street during working hours.
West 11th Street from South Hickory Street to Ann Street
Schedule:  August 2015 to October 2015
Description:  The project includes reconstruction of the sanitary sewer, water main, storm sewer, street, and lighting.
September 21 to September 25:  The landscaper continues terrace restoration.
Traffic Impacts:  W. 11th Street is closed to through traffic.  It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Parking is not permitted on the street during working hours.
9th Street from Linden Street to Center Street
Schedule:  July 2015 to October 2015
Description:  The project includes reconstruction of the water main, street, and lighting.
September 21 to September 25:  The concrete and excavation contractors will be placing curb & gutter and begin flatwork. The electrical contractor continues installing conduit for the traffic signals. The intersection is expected to re-open mid-week.
Traffic Impacts:  The intersection of Main St and 9th Street is closed to through traffic for and expected to re-open mid-week.  It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Parking is not permitted on the street during working hours.
8th Street from South Main Street to Ellis Street
Schedule:  July 2015 to October 2015
Description:  The project includes reconstruction of the water main, spot repairs of sidewalk and street.
September 21 to September 25:  The utility contractor continues installing the water services.
Traffic Impacts:  8th Street is closed to through traffic.  It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Residents, business owners, and customers may access properties past “ROAD CLOSED – LOCAL TRAFFIC ONLY” signs. Parking is not permitted on the street during working hours.

Written by: Radio Plus