East Cotton Street from North Park Avenue to McKinley Street
Schedule: May 2019 through September 2019
Description: The project includes reconstruction of the sanitary sewer, water main, storm sewer, street, and lighting.
June 10 th to June 14 th : The utility contractor will be installing sanitary and water laterals.
Traffic Impacts: East Cotton Street is closed to through traffic. Residents, business owners, and customers may access properties past “ROAD CLOSED – LOCAL TRAFFIC ONLY” signs. It is illegal to drive past a “ROAD CLOSED”
sign or to move any construction barricades. Parking is not permitted on the street within the construction zone during working hours.
McKinley Street from Rose Avenue to Stow Street
Schedule: May 2019 through September 2019
Description: The project includes reconstruction of the sanitary sewer, water main, storm sewer, street, and lighting.
June 10 th to June 14 th : The utility contractor will be installing sanitary and water laterals and storm sewer north of Arndt Street. They will also be installing sanitary main and water main south of Arndt Street.
Traffic Impacts: Traffic Impacts: McKinley Street is closed to through traffic. Residents, business owners, and customers may access properties past “ROAD CLOSED – LOCAL TRAFFIC ONLY” signs. It is illegal to drive past a
“ROAD CLOSED” sign or to move any construction barricades. Parking is not permitted on the street within the construction zone during working hours.
Stow Street from McKinley Street to Roosevelt Street
Schedule: May 2019 through September 2019
Description: The project includes reconstruction of the sanitary sewer, water main, storm sewer, street, and lighting.
June 10 th to June 14 th : The utility contractor may be installing storm sewer and laterals this week.
Traffic Impacts: Stow Street is closed to through traffic. Residents, business owners, and customers may access properties past “ROAD CLOSED – LOCAL TRAFFIC ONLY” signs. It is illegal to drive past a “ROAD CLOSED” sign or
to move any construction barricades. Parking is not permitted on the street within the construction zone during working hours.
Roosevelt Street from Rose Avenue to Arndt Street
Schedule: May 2019 through July 2019
Description: The project includes reconstruction of the sanitary sewer, water main, storm sewer, street, and lighting.
June 10 th to June 14 th : The contractor will finish excavating the roadway and placing gravel base. The electrical contractor will be installing conduit for street lights. The concrete contractor will be setting string line and placing curb and gutter near the middle of the week.
Traffic Impacts: Roosevelt Street is closed to through traffic. Residents, business owners, and customers may access properties past “ROAD CLOSED – LOCAL TRAFFIC ONLY” signs. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Parking is not permitted on the street within the construction zone during working hours.
Marquette Street from Arndt Street to McWilliams Street
Schedule: July 2019 through October 2019
Description: The project includes reconstruction of the sanitary sewer, water main, storm sewer, street, and lighting.
June 10 th to June 14 th : No work at this time.
Traffic Impacts: Marquette Street remains open to traffic.
Grove Street from Superior Street to South Military Road
Schedule: April 2019 to June 2019
Description: The project includes reconstruction of the sanitary sewer, water main, storm sewer, street, and lighting.
June 10 th to June 14 th : The contractor will be rough backfilling the new curb and placing topsoil for final terrace restoration.
Traffic Impacts: Grove Street is closed to through traffic. Residents, business owners, and customers may access properties past “ROAD CLOSED – LOCAL TRAFFIC ONLY” signs. It is illegal to drive past a “ROAD CLOSED” sign or
to move any construction barricades. Parking is not permitted on the street within the construction zone during working hours.
Intersection of Trowbridge Drive and Willow Lawn Road
Schedule: April 2019 to June 2019
Description: The project includes reconstruction of the sanitary, water extension, storm sewer, street, and lighting.
June 10 th to June 14 th : This project has been completed with no further work anticipated.
Traffic Impacts: Intersection of Trowbridge Drive and Willow Lawn Road is closed to through traffic. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Parking is not permitted on the street within the construction zone during working hours.
Tompkins Street from Superior Street to Termini
Schedule: April 2019 to June 2019
Description: The project includes reconstruction of the sanitary sewer, water main, storm sewer, street, and lighting.
June 10 th to June 14 th : Restoration work will be completed this week and final cleanup and removal of traffic control by weeks end.
Traffic Impacts: Tompkins Street from the railroad tracks to Superior Street is closed to through traffic. Residents may access properties past “ROAD CLOSED – LOCAL TRAFFIC ONLY” signs. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Parking is not permitted on the street within the construction zone during working hours.
East Second Street Bridge over DeNeveu Creek
Schedule: May 2019 through June 2019
Description: No work is planned this week. An epoxy overlay will be placed which is scheduled for the week of June 24 th . When the epoxy overlay starts the bridge will be closed for about one week. This will restrict vehicle
and pedestrian access across the bridge.
June 10 th to June 14 th : No work is anticipated until the epoxy overlay begins in mid-June.
Traffic Impacts: E. Second Street Bridge is currently open to traffic and will remain open until the epoxy overlay work begins mid-June then it will be closed to both vehicle and pedestrian access for several weeks.
Arndt Street Bridge Replacement, Arndt Street between Satterlee Street and Lincoln Avenue
Schedule: June 2019 through September 2019
Description: The project includes the replacement of the Arndt Street Bridge over the West Branch of the Fond Du Lac River. This project is a partnership between the City of Fond du Lac and the Wisconsin Department of Transportation (DOT).
June 10 th to June 14 th : The contractor will continue the removal of the existing bridge deck.
Traffic Impacts: Arndt Street between Lincoln Ave. and Satterlee Street is “Closed” to traffic as of Friday, May 31 st for the duration of the project, which is expected to last until Mid-October. There will not be a signed detour but the use of N. Hickory Street to Scott Street to N. Brook Street or the Johnson Street Bridge is
recommended.
County Road V from Pioneer Road to Fond du Lac Avenue
Pioneer Road from Sherwood Boulevard to Wedgewood Road
Schedule: April 2019 through October 2019
Description of work: The project includes reconstruction of the water main and services and partnership with Fond du Lac County for new storm sewer, street, pedestrian trail, and lighting.
June 10 th to June 14 th : Fond du Lac County Highway Dept has started work on storm water installation.
Traffic impacts: County Road V from Fond du Lac Avenue and Pioneer Road is closed to through traffic. Additionally, Pioneer Road from Sherwood Blvd to Wedgewood Lane is closed to through traffic. Residents,
business owners, and customers may access properties past “ROAD CLOSED – LOCAL TRAFFIC ONLY” signs.
Project Detour: North on Fond du Lac Avenue to South on Martin Avenue to west on Pioneer Road.