East Cotton Street from North Park Avenue to McKinley Street
Schedule: May 2019 through September 2019
Description: The project includes reconstruction of the sanitary sewer, water main, storm sewer, street, and lighting.
July 22 nd to July 26 th : The utility contractor will be installing storm sewer laterals.
Traffic Impacts: East Cotton Street is closed to through traffic. Residents, business owners, and customers may access properties past “ROAD CLOSED – LOCAL TRAFFIC ONLY” signs. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Parking is not permitted on the street within the construction zone during working hours.
McKinley Street from Rose Avenue to Stow Street
Schedule: May 2019 through September 2019
Description: The project includes reconstruction of the sanitary sewer, water main, storm sewer, street, and lighting.
July 22 nd to July 26 th : The utility contractor will be installing storm sewer laterals north of Arndt Street and  installing water and sanitary laterals south of Arndt Street.
Traffic Impacts: Traffic Impacts: McKinley Street is closed to through traffic. Residents, business owners, and customers may access properties past “ROAD CLOSED – LOCAL TRAFFIC ONLY” signs. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Parking is not permitted on the street within the construction zone during working hours.
Stow Street from McKinley Street to Roosevelt Street
Schedule: May 2019 through September 2019
Description: The project includes reconstruction of the sanitary sewer, water main, storm sewer, street, and lighting.
July 22 nd to July 26 th : The utility contractor will be installing storm sewer laterals.
Traffic Impacts: Stow Street is closed to through traffic. Residents, business owners, and customers may access properties past “ROAD CLOSED – LOCAL TRAFFIC ONLY” signs. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Parking is not permitted on the street within the construction zone during  working hours.
Marquette Street from Arndt Street to McWilliams Street
Schedule: July 2019 through October 2019
Description: The project includes reconstruction of the sanitary sewer, water main, storm sewer, street, and lighting.
July 22 nd to July 26 th : AT&T will be moving poles and underground cables.
Traffic Impacts: Marquette Street remains open to traffic.
Arndt Street Bridge Replacement, Arndt Street between Satterlee Street and Lincoln Avenue
Schedule: June 2019 through September 2019
Description: The project includes the replacement of the Arndt Street Bridge over the West Branch of the Fond Du Lac River. This project is a partnership between the City of Fond du Lac and the Wisconsin Department of Transportation (DOT).
July 22 nd to July 26 th : The contractor will continue pile driving operations at the piers into the weekend. They will be driving pile on Sat. July 20 th between 7am and 7pm. Contractor will continue working to construct the new bridge piers in the Fond du Lac River.
Traffic Impacts: Arndt Street between Lincoln Ave. and Satterlee Street is “Closed” to traffic as of Friday, May 31 st for the duration of the project, which is expected to last until Mid-October. There will not be a signed detour but the use of N. Hickory Street to Scott Street to N. Brook Street or the Johnson Street Bridge is recommended. Boat traffic under the structure will be restricted at time as work progresses.
County Road V from Pioneer Road to Fond du Lac Avenue
Pioneer Road from Sherwood Boulevard to Wedgewood Road
Schedule: April 2019 through October 2019
Description of work: The project includes reconstruction of the water main and services and partnership with Fond du Lac County for new storm sewer, street, pedestrian trail, and lighting.
July 22 nd to July 26 th : Fond du Lac County Highway Dept continues work on storm sewer installation and common excavation.
Traffic impacts: County Road V from Fond du Lac Avenue and Pioneer Road is closed to through traffic.
Additionally, Pioneer Road from Sherwood Blvd to Wedgewood Lane is closed to through traffic. Residents, business owners, and customers may access properties past “ROAD CLOSED – LOCAL TRAFFIC ONLY” signs.
Project Detour: North on Fond du Lac Avenue to South on Martin Avenue to west on Pioneer Road.