Local News

10-3-22 fdl street reconstruction schedule

todaySeptember 30, 2022

  1. Butler Street from Russell Street to Portage Street

Schedule: July 7 through October
Description: The project includes gas main and service relocations, reconstruction of sanitary sewer and laterals, storm sewer and laterals, water main and laterals, roadway, sidewalk and approaches, street lighting and restoration/landscaping.
October 3 to October 7: Concrete contractor will begin pouring sidewalk and driveway aprons
Traffic Impacts: N. Butler is closed to through traffic. Residents, business owners, and customers may access properties past “ROAD CLOSED TO THRU TRAFFIC” signs. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Parking is not permitted on the street within the construction zone during working hours.

  1. Butler Street from Forest Avenue to W. Division Street

Schedule: July 11 through October
Description: The project includes gas main and service relocations, reconstruction of sanitary sewer and laterals, storm sewer and laterals, water main and laterals, roadway, sidewalk and approaches, street lighting and restoration/landscaping.
October 3 to October 7: Concrete contractor will begin pouring sidewalk and driveway aprons
Traffic Impacts: S. Butler is closed to through traffic. Residents, business owners, and customers may access properties past “ROAD CLOSED TO THRU TRAFFIC” signs. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Parking is not permitted on the street within the construction zone during working hours.

  1. Bell Street from Bragg Street to Forest Avenue

Schedule: July 11 through October
Description: The project includes gas main and service relocations, reconstruction of sanitary sewer and laterals, storm sewer and laterals, water main and laterals, roadway, sidewalk and approaches, street lighting and restoration/landscaping.
October 3 to October 7: Concrete contractor will begin pouring sidewalk and driveway aprons
Traffic Impacts: S. Bell is closed to through traffic. Residents, business owners, and customers may access properties past “ROAD CLOSED TO THRU TRAFFIC” signs. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Parking is not permitted on the street within the construction zone during working hours. 14 th Street Reconstruction
Schedule: May 31 through October
Description: The project includes gas main and service relocations, reconstruction of sanitary sewer and laterals, storm sewer and laterals, water main and laterals, roadway, sidewalk and approaches, street lighting and restoration/landscaping.
October 3 to October 7: Contractor will continue grading for sidewalks. The Electrical contractor will begin installing conduit. Concrete Contractor will begin setting string line for curb and gutter later in the week.
Traffic Impacts: 14 th Street is closed to through traffic. Residents, business owners, and customers may access properties past “ROAD CLOSED TO THRU TRAFFIC” signs. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Parking is not permitted on the street within the construction zone during working hours.

  1. Division Street from Brooke Street to Moore Street

Schedule: September 26 through November
Description: The project includes gas main and service relocations, reconstruction of sanitary sewer and laterals, storm sewer and laterals, water main and laterals, roadway, sidewalk and approaches, street lighting and restoration/landscaping.
October 3 to October 7: Sewer Work will continue.
Traffic Impacts: W. Division Street is closed to through traffic. Residents, business owners, and customers may access properties past “ROAD CLOSED TO THRU TRAFFIC” signs. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Parking is not permitted on the street within the construction zone during working hours.
Lewis Street from Brooke Street to Dead End
Schedule: September 26 through November
Description: The project includes gas main and service relocations, reconstruction of sanitary sewer and laterals, storm sewer and laterals, water main and laterals, roadway, sidewalk and approaches, street lighting and restoration/landscaping.
October 3 to October 7: Contractor will begin Sanitary Sewer installation.
Traffic Impacts: W. Division Street is closed to through traffic. Residents, business owners, and customers may access properties past “ROAD CLOSED TO THRU TRAFFIC” signs. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Parking is not permitted on the street within the construction zone during working hours.
2022 Mill &; Overlay Program
Schedule: October 3 through October 21
Description: The project includes manhole adjustments, spot curb and gutter replacement, milling pavement, and overlay of asphalt.
Project Locations:
 Grove Street from Hickory Street to Superior Street
 Grove Street from Hickory Street, west approximately 520 feet
 Hickory Street from Johnson Street to Scott Street
 Northwest Way from Van Dyne Road west 215 feet
October 3 to October 7: Contractor will be working on various structure adjustments and repairs.
Traffic Impacts: All streets remain open to traffic.
Military Road from Western Avenue to Superior Street – WI DOT Northeast Region
Schedule: April 11-October 2022
Description: The reconstruction of S Military Rd includes reconstruction of the street and utilities, addition of bike lane and construction of a roundabout at the intersection of Military Road and 9 th Street.
October 3 to October 7: The concrete crew completed paving the southbound lane (west side) of Military Road.  Crews are working on preparing the roundabout at Ninth Street for curb and gutter, along with preparing the side roads for curb and gutter and concrete pavement. Monday, crews will seal the concrete joints of southbound once the concrete has cure. Crews will start grading for concrete driveways, sidewalk and possibly colored concrete crosswalks by weeks end.
Traffic Impacts: Military Road remains closed to through traffic. Residents, business owners, and customers may access properties past “ROAD CLOSED TO THRU TRAFFIC” signs. The intersection of Military Road and 9 th Street remains closed to traffic.
WIS 23 Expansion – Urban Section – WI DOT Northeast Region
Location/limits: WIS 23 and various intersecting local roads between US 151 and Seven Hills Road
Schedule: April 11, 2021 to fall of 2022
Description of work:  This work is part of the WIS 23 4-lane, on-alignment expansion project in Sheboygan and Fond du Lac counties.
October 3 to October 7: The contractor anticipates working on the following items:
 Begin asphalt pavement for the new trail along the project
 Place gravel shoulders on the new trail along the project.
 Complete placing colored concrete pavement and concrete sidewalk on the County K interchange.
 Complete paving the new Whispering Springs access road.
 Continue placing curb and gutter on the County UU interchange.
 Place curb and gutter, sidewalk, and colored pavement on the Highway 151 northbound off ramp to WIS 23.
Traffic impacts:
 County K north at WIS 23 – Closed
 County UU (South of WIS 23) – Closed
 County UU (North of WIS 23) – Closed
 USH 151 northbound off ramp to WIS 23: Anticipate delays while using the ramp during construction.
 WIS 23 EB lane closure from County Lane to the east: Anticipate delays while using WIS 23 eastbound during construction.

Written by: Radio Plus