Local News

7-24-23 fdl street reconstruction schedule

todayJuly 21, 2023

  1. Division Street Bridge (over DeNeveu Creek) and Concrete Rehabilitation

West of Reid Terrace to East of SSM Hospital Intersection

Description: The project includes replacing the deteriorated Division Street Bridge deck overlay, bridge approaches and sidewalk repairs. City crews will be replacing deteriorated concrete pavement east of the bridge in conjunction with the bridge work.

July 24 to July 28: The crew will complete final bridge maintenance items and cleanup the project site. We anticipate the bridge will re-open before the end of the day on Monday, July 24.

Traffic Impacts: Division Street Bridge will be closed to traffic along with one of the sidewalks across the bridge.

2023 Fond du Lac Concrete Rehabilitation

Schedule: June 28 through August 25

Description: The project includes various concrete pavement, storm inlet, and manhole rehabilitation work.

July 24 to July 28: The concrete crews have completed their work. Rolling Meadows Drive has re-opened to traffic and 4 th Street should re-open to regular traffic Thursday, July 27.

Traffic Impacts: The above streets will have partial closures and lane restriction. Please follow detours in a few locations and be “Cautious” when driving through the work zone, as lane widths are restricted.

Eleventh Street – Park Avenue to Vine Street

Description: The project includes gas main and service relocations, reconstruction of sanitary sewer and laterals, storm sewer and laterals, water main and laterals, roadway, sidewalk and approaches, street lighting and restoration/landscaping.

July 24 to July 28: Contractor will continue with water services and sanitary lateral extensions. The contractor will begin storm sewer main Installation late in the week.

Traffic Impacts: Eleventh Street will be closed to through traffic. Residents, business owners, and customers may access properties past “ROAD CLOSED TO THRU TRAFFIC” signs. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Parking is not permitted on the street within the construction zone during working hours.

Division Street – Lincoln Avenue to Railroad Tracks

Description: The project includes gas main and service relocations, reconstruction of sanitary sewer and laterals, storm sewer and laterals, water main and laterals, roadway, sidewalk and approaches, street lighting and restoration/landscaping.

July 24 to July 28: Contractor is schedule to begin storm sewer main installation starting at Gould St moving west towards Lincoln Ave late in the week.

Traffic Impacts: Division Street will be closed to through traffic. Residents, business owners, and customers may access properties past “ROAD CLOSED TO THRU TRAFFIC” signs. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Parking is not permitted on the street within the construction zone during working hours.

Ledgeview Avenue – Park Avenue to Cottage Ave Dead End

Schedule: May 8 through October

Description: The project includes gas main and service relocations, reconstruction of sanitary sewer and laterals, storm sewer and laterals, water main and laterals, roadway, sidewalk and approaches, street lighting and restoration/landscaping.

July 24 to July 28: Contractor will begin installation of storm sewer laterals.

Traffic Impacts: Ledgeview Avenue is closed to through traffic. Residents, business owners, and customers may access properties past “ROAD CLOSED TO THRU TRAFFIC” signs. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Parking is not permitted on the street within the construction zone during working hours.

Third Street – Park Avenue to Everett Street

Description: The project includes gas main and service relocations, reconstruction of sanitary sewer and laterals,  storm sewer and laterals, water main and laterals, roadway, sidewalk and approaches, street lighting and restoration/landscaping.

July 24 to July 28: No work at this time.

Traffic Impacts: Third Street remains open.

Warner Street – Ruggles Street to Forest Avenue

Description: The project includes gas main and service relocations, reconstruction of sanitary sewer and laterals,  storm sewer and laterals, water main and laterals, roadway, sidewalk and approaches, street lighting and  restoration/landscaping.

July 24 to July 28: July 10 to July 14: No work at this time.

Traffic Impacts: Warner Street remains open to traffic.