8-14-23 city of fdl street reconstruction schedule

todayAugust 11, 2023

E Johnson Street Bridge – Over DeNeveu Creek

Description: The project includes bridge restoration…repainting the bridge railing, painting the concrete parapets, curb and gutter, clearing trees and slope restoration. Crews will also install an epoxy overlay on the deck and sidewalk.

August 14 to August 18: Contractor will continue work on the bridge, clearing trees, removing stumps, replacing settled curb & gutter, installing riprap and staining the parapet. Crews will be working on the north side of the bridge this week.

Traffic Impacts: E Johnson Street will remain open to one lane in each direction. The outside lanes will be closed when crews are performing work to allow crews safe access to complete the required work. The traveling public, residents, business owners, and customers may access across bridge, but please reduce speeds and be cautious of other drivers and the crews performing work.

2023 Mill & Overlay Program

Schedule: August 7 through September 8

Description: The project includes manhole adjustments, spot curb and gutter replacement, milling pavement, and overlay of asphalt.

Project Locations:

 Roosevelt Street from Arndt Street to Winnebago Drive

 Division Street from Reid Terrace to National Avenue

 Mohawk Avenue from north of Harborview Drive to north of Boat Launch

August 14 to August 18: Contractor will be working on various structure adjustments and repairs.

Traffic Impacts: All streets remain open to traffic.

Eleventh Street – Park Avenue to Vine Street

Schedule: July 10 through September

Description: The project includes gas main and service relocations, reconstruction of sanitary sewer and laterals, storm sewer and laterals, water main and laterals, roadway, sidewalk and approaches, street lighting and restoration/landscaping.

August 14 to August 18: Contractor will begin road excavation at the beginning of the week. Electrical conduit and access box installation, as well as curb and gutter to follow later in the week.

Traffic Impacts: Eleventh Street will be closed to through traffic. Residents, business owners, and customers may access properties past “ROAD CLOSED TO THRU TRAFFIC” signs. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Parking is not permitted on the street within the construction zone during working hours.

Division Street – Lincoln Avenue to Railroad Tracks

Schedule: July 31 through October

Description: The project includes gas main and service relocations, reconstruction of sanitary sewer and laterals, storm sewer and laterals, water main and laterals, roadway, sidewalk and approaches, street lighting and restoration/landscaping.

August 14 to August 18: Contractor will continue with water main installation moving east towards Gould St.

Traffic Impacts: Division Street will be closed to through traffic. Residents, business owners, and customers may access properties past “ROAD CLOSED TO THRU TRAFFIC” signs. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Parking is not permitted on the street within the construction zone during working hours.

Ledgeview Avenue – Park Avenue to Cottage Ave Dead End

Schedule: May 8 through September

Description: The project includes gas main and service relocations, reconstruction of sanitary sewer and laterals, storm sewer and laterals, water main and laterals, roadway, sidewalk and approaches, street lighting and restoration/landscaping.

August 14 to August 18: Contractor will continue with road excavation later in the week. Contractor had to move to different street for a couple days to keep schedule.

Traffic Impacts: Ledgeview Avenue is closed to through traffic. Residents, business owners, and customers may access properties past “ROAD CLOSED TO THRU TRAFFIC” signs. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Parking is not permitted on the street within the construction zone during working hours.

Third Street – Park Avenue to Everett Street

Schedule: August 9 through October

Description: The project includes gas main and service relocations, reconstruction of sanitary sewer and laterals,  storm sewer and laterals, water main and laterals, roadway, sidewalk and approaches, street lighting and restoration/landscaping.

August 14 to August 18: Contractor will continue with water main installation.

Traffic Impacts: Third Street is closed to through traffic. Residents, business owners, and customers may access properties past “ROAD CLOSED TO THRU TRAFFIC” signs. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Parking is not permitted on the street within the construction zone during working hours.

Warner Street – Ruggles Street to Forest Avenue

Schedule: August 14 through October

Description: The project includes gas main and service relocations, reconstruction of sanitary sewer and laterals,  storm sewer and laterals, water main and laterals, roadway, sidewalk and approaches, street lighting and restoration/landscaping.

August 14 to August 18: Contractor will begin water main installation early in the week.

Traffic Impacts: Warner Street is closed to through traffic. Residents, business owners, and customers may access  properties past “ROAD CLOSED TO THRU TRAFFIC” signs. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Parking is not permitted on the street within the construction zone during working hours.