West Division Street Bridge Replacement over West Branch of Fond du lac River
Schedule: September 2023 through May 2024
Description: In partnership with the WI Department of Transportation the project includes replacing the existing bridge structure and approached. Other work includes replacing concrete pavement, sidewalk, storm sewer, grading and restoration and landscaping.
October 2 to October 6: The contractor will continue removing the existing bridge deck and start installation of the cofferdams.
Traffic Impacts: Division Street will be closed to vehicle and resident foot traffic from Brooke Street to Tallmadge until spring of 2024. Residents, business owners, and customers should find an alternate route. There is no signed detour as part of this project. Parking is not permitted in the project area as the road is closed.
Alleyway – First Street to Sheboygan Street
Schedule: September 25 through October 2023
Description: The project includes gas main and service relocations, reconstruction of storm sewer, water main, roadway, restoration/landscaping.
October 2 to October 6: Contractor will continue with storm sewer main installation from First Street heading north into Alleyway.
Traffic Impacts: The Alleyway is closed to through traffic. Pedestrians may access properties past “ROAD CLOSED TO THRU TRAFFIC” signs.
Hamilton Place – Military Road to Dead-End
Schedule: September 19 through October 2023
Description: The project includes gas main and service relocations, reconstruction of sanitary sewer and laterals, storm sewer and laterals, water main and laterals, roadway, sidewalk and approaches, street lighting and restoration/landscaping.
October 2 to October 6: Sewer contractor will continue with storm main Installation. Private side contractor will begin pipe bursting laterals from house to Right of Way.
Traffic Impacts: Hamilton Place will be closed to through traffic. Residents, business owners, and customers may access properties past “ROAD CLOSED TO THRU TRAFFIC” signs. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Parking is not permitted on the street within the construction zone during working hours.
Division Street – Lincoln Avenue to Railroad Tracks
Schedule: July 31 through October 2023
Description: The project includes gas main and service relocations, reconstruction of sanitary sewer and laterals, storm sewer and laterals, water main and laterals, roadway, sidewalk and approaches, street lighting and restoration/landscaping.
October 2 to October 6: Contractor will continue road excavation moving west. Electrical Contractor will be on site early in the week to begin installing conduit, light pole bases, and access boxes.
Traffic Impacts: Division Street will be closed to through traffic. Residents, business owners, and customers may access properties past “ROAD CLOSED TO THRU TRAFFIC” signs. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Parking is not permitted on the street within the construction zone during working hours.
First Street – Military Road to E. Branch Fond du lac River
Schedule: October 2 through October 2023
Description: The project includes reconstruction of water main and laterals, spot repair roadway, sidewalk and approaches and restoration/landscaping.
October 2 to October 6: Sewer contractor will begin water main installation.
Traffic Impacts: First Street should remain open to traffic; however short term lane restrictions/closure may be necessary at times. Parking is not permitted on the street within the construction zone during working hours.
Third Street – Park Avenue to Everett Street
Schedule: August 9 through October 2023
Description: The project includes gas main and service relocations, reconstruction of sanitary sewer and laterals, storm sewer and laterals, water main and laterals, roadway, sidewalk and approaches, street lighting and restoration/landscaping.
October 2 to October 6: Excavation contractor will begin road excavation mid-week.
Traffic Impacts: Third Street is closed to through traffic. Residents, business owners, and customers may access properties past “ROAD CLOSED TO THRU TRAFFIC” signs. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Parking is not permitted on the street within the construction zone during working hours.
Warner Street – Ruggles Street to Forest Avenue
Schedule: August 9 through October 2023
Description: The project includes gas main and service relocations, reconstruction of sanitary sewer and laterals, storm sewer and laterals, water main and laterals, roadway, sidewalk and approaches, street lighting and restoration/landscaping.
October 2 to October 6: No work anticipated for the week.
Traffic Impacts: Warner Street is closed to through traffic. Residents, business owners, and customers may access properties past “ROAD CLOSED TO THRU TRAFFIC” signs. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Parking is not permitted on the street within the construction zone during working hours.