Local News

10-16-23 fdl street reconstruction schedule

todayOctober 13, 2023

West Division Street Bridge Replacement over West Branch of Fond du lac River

Schedule: September 2023 through May 2024

Description: In partnership with the WI Department of Transportation the project includes replacing the existing bridge structure and approached. Other work includes replacing concrete pavement, sidewalk, storm sewer, grading  and restoration and landscaping.

October 16 to October 20: The contractor will continue to form the west abutment and start driving piling for the west abutment.

Traffic Impacts: Division Street will be closed to vehicle and resident foot traffic from Brooke Street to Tallmadge until spring of 2024. Residents, business owners, and customers should find an alternate route. There is no signed detour as part of this project. Parking is not permitted in the project area as the road is closed.

Alleyway – First Street to Sheboygan Street

Schedule: September 25 through October 2023

Description: The project includes gas main and service relocations, reconstruction of storm sewer, water main, roadway, restoration/landscaping.

October 16 to October 20: Contractor will be in early next week to clean up work area and mobilize equipment out.  No other work is anticipated for the week.

Traffic Impacts: The Alleyway is closed to through traffic. Pedestrians may access properties past “ROAD CLOSED TO THRU TRAFFIC” signs.

Hamilton Place – Military Road to Dead-End

Schedule: September 19 through October 2023

Description: The project includes gas main and service relocations, reconstruction of sanitary sewer and laterals, storm sewer and laterals, water main and laterals, roadway, sidewalk and approaches, street lighting and restoration/landscaping.

October 16 to October 20: Restoration contractor might begin topsoil and seed in Hamilton Park. Road excavation contractor might begin cutting road to subgrade and placing aggregate mid to late week.

Traffic Impacts: Hamilton Place will be closed to through traffic. Residents, business owners, and customers may access properties past “ROAD CLOSED TO THRU TRAFFIC” signs. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Parking is not permitted on the street within the construction zone during working hours.

Division Street – Lincoln Avenue to Railroad Tracks

Schedule: July 31 through October 2023

Description: The project includes gas main and service relocations, reconstruction of sanitary sewer and laterals, storm sewer and laterals, water main and laterals, roadway, sidewalk and approaches, street lighting and restoration/landscaping.

October 16 to October 20: Paving contractor will continue to prepare base ahead of concrete pour. Pavement placement to continue mid-week.

Traffic Impacts: Division Street will be closed to through traffic. Residents, business owners, and customers may access properties past “ROAD CLOSED TO THRU TRAFFIC” signs. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Parking is not permitted on the street within the construction zone during working hours.

First Street – Military Road to E. Branch Fond du lac River

Schedule: October 2 through October 2023

Description: The project includes reconstruction of water main and laterals, spot repair roadway, sidewalk and approaches and restoration/landscaping.

October 16 to October 20: No work is anticipated.

Traffic Impacts: First Street should remain open to traffic; however short term lane restrictions/closure may be necessary at times. Parking is not permitted on the street within the construction zone during working hours.

Third Street – Park Avenue to Everett Street

Schedule: August 9 through October 2023

Description: The project includes gas main and service relocations, reconstruction of sanitary sewer and laterals, storm sewer and laterals, water main and laterals, roadway, sidewalk and approaches, street lighting and restoration/landscaping.

October 16 to October 20: Excavation contractor will finish pulling sidewalk. Driveway aprons and sidewalk  placement mid to late week.

Traffic Impacts: Third Street is closed to through traffic. Residents, business owners, and customers may access properties past “ROAD CLOSED TO THRU TRAFFIC” signs. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Parking is not permitted on the street within the construction zone during working hours.

Warner Street – Ruggles Street to Forest Avenue

Schedule: August 9 through October 2023

Description: The project includes gas main and service relocations, reconstruction of sanitary sewer and laterals,  storm sewer and laterals, water main and laterals, roadway, sidewalk and approaches, street lighting and restoration/landscaping.

October 16 to October 20: Road excavation contractor will continue with road excavation and base placement.  Electrical contractor will begin installing conduit.

Traffic Impacts: Warner Street is closed to through traffic. Residents, business owners, and customers may access  properties past “ROAD CLOSED TO THRU TRAFFIC” signs. It is illegal to drive past a “ROAD CLOSED” sign or to move  any construction barricades. Parking is not permitted on the street within the construction zone during working hours.

Written by: Radio Plus

Post comments (0)

Leave a reply

Your email address will not be published. Required fields are marked *